Plantations

Down to Earth No. 44, February 2000

Community anger is being directed at the newly completed plant in South Sumatra

The PT TEL paper pulp factory at Muara Enim, South Sumatra was completed in November 1999 and started production trials in December with a view to full production by January 2000.

Down to Earth No. 42, August 1999

A long-running land dispute between oil palm plantation company PT London Sumatra and indigenous Dayak landowners has resulted in large-scale military and police repression in East Kalimantan.

Down to Earth No. 42 1999

Construction of the US$1 billion PT Tanjung Enim Lestari (PT TEL) paper pulp plant in Muara Enim, South Sumatra, is nearly complete. Hundreds of contract workers will be laid off soon. Most of the equipment, from Scandinavian, Canadian and German companies backed by export credit agreements from their governments, has been installed. Production is expected to start in October. The plant's capacity is 450,000 tonnes of pulp per year.