BP - Tangguh

DTE raises critical questions about the giant Tangguh natural gas and LNG project, operated by BP in Bintuni Bay, West Papua.

Now in the production phase, this multi-billion dollar project has brought rapid and massive change to local communities whose customary lands have been used to site the project.

DTE has questioned BP about human rights, social and environmental impacts and the wider political context and reports extensively about Tangguh.

Clearing land for the Tangguh project construction

Down to Earth No 65  May 2005

In February 2004, DTE took a detailed look at BP's controversial gas project in Bintuni Bay, West Papua. One year on, we ask how far concerns over human rights, security and local people's rights have been addressed.

The Tangguh gas extraction and liquid natural gas (LNG) installation in the Bird's Head region of West Papua got the final go-ahead from BP on March 7th. As a result, the area will experience massive social, environmental and economic changes.

Down to Earth No 65  May 2005

Statement by the people of Soway, Wayuri & Simuna as the landowners of the site where the Tangguh natural gas project is being developed.

 

To the Indonesian Oil & Gas Management Body - BPMigas

We have reviewed the process and documents relating to the loss of traditional rights of the Simuna, Soway, Wayuri people in connection with the Tangguh natural gas project under development by Pertamina and BP, facilitated by the Manokwari local government in 1999.

Down to Earth No 65  May 2005

The following letter, slightly abridged here, was addressed to Lord John Browne, CEO of BP, and is dated December 8th 2004.

As individuals and organisations in West Papua and internationally who are closely following the Tangguh LNG Project in West Papua, we are writing to express our mounting concerns and to call for your immediate intervention…

…Our concerns are centred on:

  • inadequate progress on key human rights commitments
  • a worrying lack of transparency
  • a fai

Down to Earth No 65  May 2005

Status of the project

The 'final investment decision' to proceed with Tangguh came on March 7th, after many delays. The construction phase of the US$5 billion project is now expected to start in late 2005. Tangguh will be operational in 2008, with two full gas production units or 'trains' (Reuters7/Mar/05, TIAP 2004).

Down to Earth No. 60, February 2004

With the political context worsening and militarisation in West Papua increasing, BP's commitments to human rights and its 'community-based security policy'- look more and more flimsy.

In 2003, West Papua continued to suffer the impacts of Indonesian military repression.

Down to Earth No 57 May 2003

Two studies commissioned by BP have highlighted serious concerns over the impact of the planned Tangguh gas project in West Papua.

BP has announced the findings of two studies it commissioned to examine the potential impacts of the Tangguh gas project in Bintuni Bay, West Papua, on human rights, local communities and the environment.

Down to Earth No 55  November 2002


This report is by Katie Wilson, president of the Oxford West Papua Friendship Society, who visited Bintuni Bay earlier this year with an expedition from Oxford University.

BP's Tangguh liquid natural gas project in West Papua will make BP Indonesia's largest single foreign investor. It will also profoundly affect the environment and social structure of Bintuni Bay, one of West Papua's most remote and undeveloped regions.